In brief: Passivation records prove that each wetted part of new stainless steel equipment was passivated, how it was done and that it passed a test. EU GMP Annex 15 says that, where justified, documentation review and some tests performed at the factory acceptance test (FAT) need not be repeated at IQ or OQ, if transport and installation do not affect them. IQ includes verification of the materials of construction. ASTM A967 offers several alternative tests, such as water immersion, high humidity and copper sulfate, plus a free iron test. A complete record names the part, method and chemical, strength and temperature, contact time, rinse, test result and who did it.
The vessel is built, polished and ready to ship. Then the buyer's QA team arrives for the factory acceptance test and asks one question. Where are the passivation records? If the answer is a single line on a delivery note, the handover can stall. This guide is for OEMs and fabricators who build stainless steel equipment for pharma and food plants.
It covers what passivation records should hold, why buyers ask for them at FAT and SAT, and which tests prove the steel is passive. Getting these right means fewer repeat checks once the equipment reaches site.
They are the papers that prove each wetted part of the equipment was passivated, how it was done and that it passed a test. They travel with the equipment from the workshop to the buyer's site. The buyer's QA team may review them at the factory acceptance test (FAT), the site acceptance test (SAT) and installation qualification (IQ).
Passivation is an acid treatment for stainless steel. It removes free iron, the loose iron specks left by cutting and welding. It helps the steel's thin chromium oxide layer form again. That layer is what stops rust. A buyer cannot see it, so the record is their main proof that the job was done.
These handover papers sit alongside the plant's own logs. Our guide on passivation documentation that fails audits covers the records a plant keeps after the equipment is in use. This guide covers the step before that: what the maker hands over.
Because what is checked well at the factory may not need checking again at site. The EU's guide on qualification, EU GMP Annex 15, allows that. Where justified, it says "documentation review and some tests could be performed at the FAT" without repeating them at IQ or OQ. Weak records remove that option.
The same rule has a condition. The FAT result can only stand if "the functionality is not affected by the transport and installation." So buyers often check the records at FAT and the surfaces again at SAT. A record that is complete at the factory makes that second check quick.
Annex 15 also makes FAT a choice. Section 3.4 says equipment "may be evaluated, if applicable, at the vendor prior to delivery." Section 3.7 adds that "FAT may be supplemented by the execution of a SAT" once the equipment arrives. With or without a FAT, a buyer will usually want to see the passivation records before the equipment goes into use.
At IQ, Annex 15 lists two checks that touch your papers. One is "Verification of the materials of construction". The other is collecting the maker's operating and upkeep papers. Annex 15 does not name passivation records. Even so, many buyers file them in the same IQ pack.
US plants have their own reason. 21 CFR 211.67 says "Records shall be kept of maintenance, cleaning, sanitizing, and inspection". A buyer who sells to the US will want your records to fit into that system.
Enough detail for a stranger to repeat the job and check the result. That comes down to seven fields. They cover the part, the method, the chemical's strength and temperature, the time and the rinse. The last two are the test result and who did the work. A record missing any of these will draw questions at FAT.
| Field | What to write | Why the buyer needs it |
|---|---|---|
| Item and area treated | Tag number, drawing and surfaces covered | Links the record to the right part |
| Method and chemical | For example, citric acid, with the product name | Shows which method in the spec was used |
| Strength and temperature | The concentration and the bath or surface temperature | Proves the method's limits were met |
| Contact time | Start and finish times | Shows the steel was treated long enough |
| Rinse | Water quality and how the rinse was done | Shows the acid was fully removed |
| Test and result | The test name, the spot tested and pass or fail | Proves the steel is passive |
| Who and when | Names, signatures and dates | Shows who is responsible for the work |
Other industries ask for similar fields. The Open Compute Project wrote a 2026 guide for data center cooling loops. It asks teams to "Record the date, passivation method used, chemical concentrations, exposure time and test results." Those cover parts of five of the seven fields above.
ASTM A967 is the usual reference, and it offers a choice. Its scope says it "includes several alternative tests, with acceptance criteria". The buyer's spec or purchase order should name the one that applies. Agree it before work starts, so the test you run is the one the buyer will accept at FAT.
The ASTM A967 summary lists the tests. They are the "water immersion test, high humidity test, salt spray test, copper sulfate test, and potassium ferricyanide-nitric acid test." It also calls for a free iron test to check for loose iron on the surface. The current edition is A967/A967M-25.
Each test suits a different job, part size and setting. Our guide on passivation testing methods explains how each one works and when to use it.
A967 also sets what the surface should look like. Passivated parts "shall exhibit a chemically clean surface". On visual inspection, they should "show no etching, pitting, or frosting". Write the visual check into the record, too.
The rinse belongs in the record as well. A967 says that straight after the acid, parts "shall be thoroughly rinsed". It allows still, countercurrent or spray rinses, alone or together. Write down which one you used and the water quality, so the buyer can see no acid was left behind.
They form one chain from the workshop to the plant. The URS sets what the buyer needs. The OEM passivates the equipment and records it. FAT reviews the records and the steel at the workshop. SAT can recheck the steel after transport. At IQ, the materials are checked and the papers filed.
Transport is the weak link. Scratches, road dust or water left inside during shipping can undo good work. Cap every opening and keep the equipment dry on the way. If any welding is done at site, the new welds need passivation and a fresh record of their own. Note any damage found at SAT in the same file, with photos, so each fix can be traced.
Our guide to passivation onsite or offsite helps you decide where each part of the job should happen.
Gaps, vague words and records that do not match the spec. The usual problems are easy to spot once you know them. A line that says "passivated as per ASTM" with no method, no test and no date is the classic case. So is a test result with no place, part or person named next to it.
Here are the gaps to check for before FAT:
We passivate equipment at your workshop or at our premises, and every job comes with all the relevant documents. Before work starts, we can agree with you which fields your buyer needs. Our team checks the surface with imported tools that are fully calibrated. We can also polish or electropolish the steel before we passivate it.
Our three directors bring 60+ years of combined industry experience. Fabricators with a steady flow of passivation work can bring it in-house. Our service for the establishment of a passivation system helps OEMs and pipe spool makers set up their own passivation system at their workshop.
Here is a made-up example of a complete record at work. Say a fabricator in Vadodara builds a mixing vessel for a plant near Hyderabad, with FAT set for November. The buyer's URS names a citric acid method and a high humidity test. The record lists both, with the tag number, times and signed results. FAT closes the passivation item in one review.
Remember one thing: the buyer cannot see passivation, so your record has to show it for you. Before your next FAT, pull out the last passivation record you sent to a buyer. Read it as if you were their QA team seeing it for the first time.
Check it against the seven fields in this guide. Mark any field that is missing or vague, and fix the form before the next job. If you need help with the passivation itself, or with setting up your own passivation system, call us. We reply within 24 hours.
Not always. Annex 15 uses the word "may" for a FAT at the maker's site, so it is a choice. Buyers often hold one for complex equipment, and the passivation records are reviewed there.
The one your buyer's spec or purchase order names. ASTM A967 offers several tests, such as water immersion, high humidity and copper sulfate. Agree the test before work starts so it is accepted at FAT.
Sometimes. Where justified, Annex 15 says document reviews and some tests at FAT need not be repeated at IQ or OQ. That only holds if transport and installation do not affect the result, so many buyers still check the steel at SAT.
Yes. A weld made at site has not been through the workshop treatment. Passivate it, test it and record it with its own tag, date and result.
The buyer files them with the equipment's qualification papers, and keeps them in their own records system. The OEM should keep a copy too, in case questions come up later.
Sources. European Commission, EU GMP Annex 15: Qualification and Validation (30 March 2015), sections 3.4 to 3.9, for FAT, SAT, documentation review at FAT and IQ checks · ASTM International, ASTM A967/A967M-25 summary, for the alternative tests, the free iron test and the clean surface requirement · US Code of Federal Regulations, 21 CFR 211.67(c), for records of maintenance, cleaning, sanitizing and inspection · Open Compute Project, Guidelines for Using Propylene Glycol-Based Heat Transfer Fluids in Liquid Cooled Racks (September 2026), for its list of passivation record fields. Every quotation was read on the source. The seven record fields and the list of common gaps are ours. The Vadodara fabricator is a made-up example for illustration.